top of page

LaSalle Canal MGP Sediment RemedIATION

bc-logo-block.jpg

PROJECT SUMMARY

Bluff City Materials, Inc. (BCM), D Construction (D) and White Lake Dock and Dredge, Inc. (WLDD) are currently executing the largest In-Situ Stabilization of MGP Impacted Sediments in a water body.  The team was contracted by Ameren Energy Services, Inc. in the Fall of 2018.   The key elements of the project include: Canal sediment dredging, Sheet pile installation, In-situ sediment stabilization, force main replacement, upland site soils and sediment management, water treatment and site restoration.  The key elements of the project include:

​

  • Dredging – 77,000 cubic yards of MGP impacted sediment

  • In-situ Stabilization – 70,000 cubic yards of MGP impacted sediment to a depth of 25 feet

  • Sheet Pile Installation – Coffer Dam 13,640 SF 325 (LF); Canal Access Pier 92,012 SF (180 LF)

  • Off-site Transportation and Disposal – 172,000 tons

  • Sediment staging area/dewatering cell operation – 174,500 tons

  • Forcemain installation – 52’ diameter, 50-foot depth, 450 FT length.
     

The project team was responsible for completing a 100% design for the project.  This included core sampling, stabilization treatability study, full-scale pilot demonstration and final design drawings.  Several new innovative technologies have been employed to execute the LaSalle project.  These included the following:

​

  • Delmag RH 30 and RH 34 drill rigs with operator activated grout feed and real time process monitors.

  • Scheltzke 1030 automated batch plants, diesel powered with piston grout pumps.

001.jpg

PROJECT KEY HIGHLIGHTS

Client: Ameren Energy

Location:  LaSalle, Illinois

​

  • Removal of MGP Soils

  • In-Situ Stabilization

  • Sheet Pile Installation


Contract Value: $30,000,000
Performance Dates: November 2018 to December 2019

bottom of page