LaSalle Canal MGP Sediment RemedIATION
PROJECT SUMMARY
Bluff City Materials, Inc. (BCM), D Construction (D) and White Lake Dock and Dredge, Inc. (WLDD) are currently executing the largest In-Situ Stabilization of MGP Impacted Sediments in a water body. The team was contracted by Ameren Energy Services, Inc. in the Fall of 2018. The key elements of the project include: Canal sediment dredging, Sheet pile installation, In-situ sediment stabilization, force main replacement, upland site soils and sediment management, water treatment and site restoration. The key elements of the project include:
​
-
Dredging – 77,000 cubic yards of MGP impacted sediment
-
In-situ Stabilization – 70,000 cubic yards of MGP impacted sediment to a depth of 25 feet
-
Sheet Pile Installation – Coffer Dam 13,640 SF 325 (LF); Canal Access Pier 92,012 SF (180 LF)
-
Off-site Transportation and Disposal – 172,000 tons
-
Sediment staging area/dewatering cell operation – 174,500 tons
-
Forcemain installation – 52’ diameter, 50-foot depth, 450 FT length.
The project team was responsible for completing a 100% design for the project. This included core sampling, stabilization treatability study, full-scale pilot demonstration and final design drawings. Several new innovative technologies have been employed to execute the LaSalle project. These included the following:
​
-
Delmag RH 30 and RH 34 drill rigs with operator activated grout feed and real time process monitors.
-
Scheltzke 1030 automated batch plants, diesel powered with piston grout pumps.
PROJECT KEY HIGHLIGHTS
Client: Ameren Energy
Location: LaSalle, Illinois
​
-
Removal of MGP Soils
-
In-Situ Stabilization
-
Sheet Pile Installation
Contract Value: $30,000,000
Performance Dates: November 2018 to December 2019