top of page

IMPACTED SEDIMENT DREDGING

bc-logo-block.jpg

PROJECT SUMMARY

BCM Remediation (BCM) was engaged by NRG Energy, Inc. (NRG) to remove potentially impacted sediments from the stations Lakeside Cooling System Outlet and Cooling Intake Canal, 50,000 cubic yards of sediment were dredged from the Lakeside Cooling System Outlet and 15,000 cubic yards of sediment were dredged from the Cooling Intake Canal.  This activity was conducted in the middle of the winter in Lake Michigan. The dredging had to be conducted between December and March as to not disturb the Great Lakes Piping Plover nesting in the area of the power plant.  CAT 349 Excavators were modified to allow operation in extreme weather conditions. Temporary access roads were constructed into Lake Michigan to allow dredging to a depth of 12 foot.  The dredged sediment was transported to an on-site material management facility.

​

The scope of work of work included;

  • Mobilization,

  • Dredging Lake Side – 50,000 cubic yards,

  • Dredging Intake Canal – 15,000 cubic yards,

  • Transportation and placement of sand at sediment storage area,

  • Management of sediment storage area,

  • Utilization of biodegradable hydraulic oils in excavators, and,

  • Demobilization

IMG_4302a.jpg

PROJECT KEY HIGHLIGHTS

Client: NRG Energy, Inc.

Location:  Waukegan, Illinois


Contract Value: $600,000.00
Performance Dates: January 2019 – March 2019

bottom of page